05 Quiz: Scrum Fundamentals
Instructions
This is an interactive quiz testing your understanding of Scrum fundamentals from Chapter 05.
- Select your answer for each question
- Get immediate feedback on your choices
- Retry questions as many times as you need
- Track your progress across sessions
Topics covered:
- Scrum Roles (PO, SM, Development Team)
- The Scrum Board and WIP
- V-Model vs. Agile
- Sprint Events (Planning, Daily, Review, Retrospective)
A customer approaches the team during a sprint and says “I need this new feature added immediately!” Who should respond to this request?
The Development Team has been blocked for two days because they need access to a production server, but the IT department hasn’t responded to their request. Who should escalate this?
The team is debating whether to use React or Vue.js for the frontend. There are valid arguments for both. Who makes the final decision?
At the Sprint Review, the team demonstrates a feature that works but doesn’t quite match what the stakeholders expected. Who has the authority to accept or reject this work?
During Sprint Planning, the Product Owner says “I want Developer A to work on the database task because they’re the expert.” Is this appropriate?
A new Scrum Master starts tracking how many tasks each developer completes per day and uses this data in their performance reviews. What’s wrong with this approach?
In a small team of 4 people, can one person be both the Product Owner and a Developer?
You look at the team’s Scrum board and see: 0 items in “To Do”, 8 items in “In Progress”, 1 item in “Review”, 0 items in “Done”. The sprint is 50% complete. What does this indicate?
The Scrum board hasn’t changed in 3 days. The Daily Scrum discussions are brief with “still working on the same thing” from everyone. What’s likely happening?
During the sprint, the Product Owner sees that a high-priority item is still in “To Do” and moves it to “In Progress” themselves, assigning it to a specific developer. What’s wrong with this action?
A team argues that they don’t need a physical or digital board because they have good communication and everyone knows what everyone else is working on. What’s the main risk of skipping the board?
In the V-Model, testing happens after development is complete. What is the primary problem this causes?
The V-Model assumes “we can know all requirements upfront.” Why is this assumption problematic?
A major requirement changes 6 months into a 12-month V-Model project. What typically happens?
Despite its limitations, the V-Model may still be appropriate in some contexts. Which scenario might justify using a V-Model approach?
What are the TWO key outputs of Sprint Planning?
What is the primary purpose of the Daily Scrum (standup)?
What’s the key difference between Sprint Review and Sprint Retrospective?
Under what circumstances can a Sprint be cancelled before its end date?
The team’s retrospective identifies that “code reviews take too long and block progress.” What should happen next?